# Budget allocations

> Connect a budget line to the correct target, timing, amount mode, and configured status.

A budget allocation relates one budget line to one configured target. It can represent a fixed amount or a percentage, a timing/frequency setting, a period, an overview/details field, and a configured status. It is a planning/control record, not a payment, procurement approval, accounting posting, cash reservation, or proof of actual spend.

The Syrian Citizen Services Directorate allocates the Regional Adviser Training line to the Digital Citizen Intake Modernization project, then allocates a separate line to a regional service centre. Each allocation starts from the correct budget and budget line.

## When to use it

Use an allocation when the directorate needs to associate part of a budget line with a project, plan, goal, output, activity, task, node, location, assignment, position, or another target option shown in the deployed workspace.

Choose only targets available in the current form. The underlying model can support a wider set of target types, while older/specialized screens may offer a narrower list. Do not document or select a target solely because it exists in another organization’s configuration.

## Configuration

| Field                  | What to configure                                           | Important behavior                                                                                        |
| ---------------------- | ----------------------------------------------------------- | --------------------------------------------------------------------------------------------------------- |
| Budget                 | Required budget record                                      | Choose this first. It determines which budget lines are valid.                                            |
| Budget line            | Required line from the selected budget                      | The line selector is constrained to the chosen budget.                                                    |
| Target type and target | Required configured target category and record              | Relates the allocation to work/structure; it does not identify an approval owner or payment recipient.    |
| Allocation mode        | Fixed amount or percentage where enabled                    | Percentage mode uses the selected line’s planned amount as its source in the current allocation metadata. |
| Amount/percentage      | Fixed amount or percentage value                            | Percentage must be within 0–100 in the supplied form.                                                     |
| Timing                 | Frequency and start/end dates where enabled                 | End date cannot be before start date in the supplied form.                                                |
| Status/details         | Deployed configured status and explanatory overview/details | Use only available status values and approved narrative information.                                      |

The standard source metadata supports planned, released, committed, in-use, closed, and cancelled allocation states. Treat these as configured operational states. None proves an accounting entry, supplier commitment, public-finance approval, or actual expenditure on its own.

## Workflow

1. Open Budget allocations and identify the target purpose before choosing values.
2. Select the budget.
3. Select the budget line that belongs to that budget and represents the intended purpose.
4. Choose the target type visible in the deployed form, then choose the target record.
5. Select fixed amount or percentage where the form offers that choice. Enter the reviewed amount/percentage.
6. Set the frequency and dates if they are enabled. Check that the end date is not earlier than the start date.
7. Select the configured status and add concise details/overview where needed.
8. Save, then re-open the allocation and verify budget, line, target, amount mode, dates, and status together.

## Worked example

The Directorate assigns part of its regional-training line to the intake-modernization project.

> Budget: BUD-INTAKE-2026
> Budget line: TRAIN-REGIONAL — Regional adviser training
> Target type: Project
> Target: PRJ-DIGITAL-INTAKE-2026
> Mode: Percentage
> Percentage: 40
> Period: the approved training period
> Status: choose the status available in the deployed workspace

If the line’s planned amount is 10,000 in the configured currency, a 40% percentage allocation derives a 4,000 committed amount in the current metadata model. That is a planning calculation. It does not establish that 4,000 is paid, encumbered in an accounting system, or legally committed.

For the regional service-centre allocation, choose the Location or Node target only if it accurately represents where the planned use belongs. Do not select an assignment merely because a person is associated with the work.

## Testing

Use a temporary budget, line, target, and allocation with non-sensitive values.

1. Create a temporary budget with two temporary lines.
2. Select the budget and confirm that only its lines are selectable.
3. Create one fixed-amount allocation and one percentage allocation for different temporary targets.
4. Attempt a percentage below 0 or above 100 and confirm validation prevents it.
5. Attempt an end date before the start date and confirm validation prevents it.
6. Re-open the saved test allocation to verify the complete relationship, then retire the test data.

Never test allocation status or amount behavior against a live operational budget without the appropriate financial review.

## Troubleshooting

| Situation                                      | Check                             | Resolution                                                                                                                    |
| ---------------------------------------------- | --------------------------------- | ----------------------------------------------------------------------------------------------------------------------------- |
| No budget line is available                    | Selected budget                   | Select/save the intended budget first and verify the line belongs to it.                                                      |
| The target list is different from this guide   | Deployed allocation configuration | Use only target types shown in the form and update documentation after a verified configuration change.                       |
| The percentage cannot be saved                 | Percentage range                  | Enter a value from 0 through 100 and check the selected amount mode.                                                          |
| The date range is rejected                     | Start/end dates                   | Make the end date equal to or later than the start date.                                                                      |
| A reviewer assumes the allocation is a payment | Record boundary                   | Check the organization’s separate procurement/accounting/payment process; an allocation is not proof of any of those actions. |

## Permissions and data-quality limits

Budget allocation access is controlled by the allocation entity capability and potentially the record’s scopes. Budget or project ownership does not automatically grant create/update/delete access.

Keep the target relation and narrative details factual. Do not treat an allocation status, amount, or percentage as an approval, actual expense, accounting posting, legal commitment, or citizen-service performance measure.

![ Illustrative KayanOS budget allocation for a representative service-centre activity. ](https://kayanos.app/docs-images/en/projects/budget-allocations.png)

## Related guides

* Create the source records in [Budgets](/projects/budgets).
* Define the service initiative in [Projects](/projects/projects).
* Review workforce/project time in [Shifts and timesheets](/government-operations/shifts-and-timesheets).